Proof Test Interval at you Plant??

Posted: 26 Apr 2010, 13:06
by sameenkhan
Hi Guys,

For a SIS, what typical Proof Test interval is set at your plant??

Regards,
Sameen

Re: Proof Test Interval at you Plant??

Posted: 09 Aug 2010, 10:09
by ali.abbas
Sameen,

At our plant, the current practice is to check the primary sensing element on an annual basis.
Complete logic verification is carried out once in 1 or 2 years or during plant outage depending on
1- criticality of service
2- whether the activity can be carried online or not.
Hope your questions answered.

Regards,
Ali Abbas