Responsibility of LOPC calculations

Chemical engineering, Plant designs related to chemical, petro-chemical or oil&gas, Operational assistance, etc.
Post Reply
chem51
Posts: 31
Joined: 30 Jul 2026, 20:34
Location: ''
Contact:

Responsibility of LOPC calculations

Post by chem51 »

Who should be responsible to perform calculations of LOPC quantification after an incident?
ivani1
Posts: 159
Joined: 25 May 2025, 14:25
Area of interest: Mechanical Engineering

Re: Responsibility of LOPC calculations

Post by ivani1 »

This is with process safety engineer or process engineer of the site. Should be run as and when leak is reported to get all the basic data. Once delayed, it may affect reporting, and getting the right information which is available with the operations shift witnessing the leak, and the maintenance staff responsible to fix that.
ww2i
Posts: 112
Joined: 20 Nov 2025, 21:06
Area of interest: Petroleum Engineering

Re: Responsibility of LOPC calculations

Post by ww2i »

Company is required to have a qualified loss prevention / HSE /Process Safety engineer to run these calculations.
It is important to manage this whole process in a way that immediate reporting is done along with the analysis, the same day when the leak has been reported.
There are parameters which are required to be recorded to have these calculations accurately depicting the right Tier level.
Many a times, a leak which is either Tier-2 or 1 is required to be reported to authorities within 24h basis.
chem51
Posts: 31
Joined: 30 Jul 2026, 20:34
Location: ''
Contact:

Re: Responsibility of LOPC calculations

Post by chem51 »

We have been thinking about having this as a shared responsibility of Operations, Process, HSE, and Process Safety Engineer.
All we could see was the sheet itself is required to be provided with inputs available with the reporting party (mostly Operations), report goes to HSE for their initial assessment, Process is likely to provide details on the system and yes Process Safety Engineer would be the authority to make a final call once the calculations are done.