We have been finding issues, reporting them, and sometimes they are implemented and some other times, they are not.
This takes us to a situation that an estimated target date is already breached and inspection findings may still not be valid any more - deteriorated further.
What are the practices at your places to control such issues?
Managing Inspection Follow-up
Re: Managing Inspection Follow-up
First when the inspection recommendation is issued, it must have a target date not only for implementation of action but performing an inspection as a follow up to ensure that damage rate has not been exceeding. \nSecond in case target date of implementation is gone, a re-assessment must be made and the matter should be escalated.
-
Guest
Re: Managing Inspection Follow-up
This one stands as a challenge and we have seen many incidents happening due to a long standing inspection recommendation. Many sites deal such issues in many different ways however till the recommendation is not implemented there has to be a goverance in place by Inspection. I have not seen execution parties taking care of such pending cases until or unless the priority is set to HIGHEST. And Priority is required to be defined by Inspection only.