Line spading controls

Operational issues of any Petrochemical plant or Oil and gas field, upstream issues, etc.
Post Reply
ww2i
Posts: 106
Joined: 20 Nov 2025, 21:06
Area of interest: Petroleum Engineering

Line spading controls

Post by ww2i »

How the line spading controls can be put in place making sure that when unit is started back up with some spades still in place, there should not be any process or engineering concern?
Do not tell me that PSSR run should be the only one to assess this.
And if that is then should we be expecting participants in PSSR to closely perform engineering judgements as well? That too line by line?
jeem
Posts: 124
Joined: 10 Aug 2025, 17:25
Area of interest: Chemical Engineering

Re: Line spading controls

Post by jeem »

First of all, spaded lines during startup should be identified as part of permit system. If they are spaded, there must be an active permit. Or if spade has been put for a longer period of time and remaining system is charged up, there should have been an MOC in place support with some risk assessment supporting that line can be kept spaded with other associated system charged up.
But interestingly, spaded lines are normally picked up during PSSR only as most of the spading is done during shutdown opportunity.
mechcolor
Posts: 323
Joined: 17 May 2010, 18:05
Area of interest: Manufacturing Engineering

Re: Line spading controls

Post by mechcolor »

Putting spades required a management of change process where you get your spade design approved through the committee.
Now this is when you are using spades while the system is down.
Once you are charging back up with some spades still in location, a risk review supported with change management process stands mandatory. Do not let that go unchecked as some of the times, we just blind one end of the line and take rest of the system in service. Yes, take the system in service after carefully looking into the spaded portion for any of the risk it might be carrying on the piping configuration of itself with the process system requirements.
ivani1
Posts: 149
Joined: 25 May 2025, 14:25
Area of interest: Mechanical Engineering

Re: Line spading controls

Post by ivani1 »

Spade control should not depend on the PSSR team discovering, line by line, that a spade has been left in the wrong position. That is a weak control philosophy.
The better approach is to treat temporary spading/blinding as a controlled configuration of the process plant, with independent controls at several stages. PSSR then becomes a final verification, not the primary mechanism for discovering engineering incompatibilities.
The key principle is that every spade should have a defined purpose, location, status, owner, and required removal condition.
More importantly, the system should distinguish between:
Spades required for normal operation — intentionally left in place.
Spades installed for maintenance/isolation — must be removed before startup.
Spades whose continued presence is acceptable only under a defined operating condition — e.g., equipment out of service, alternate flow path available.
Spades that would create a process safety or equipment integrity problem if left installed.
The last category is where engineering judgement needs to be captured before startup, not improvised during PSSR.
ww2i
Posts: 106
Joined: 20 Nov 2025, 21:06
Area of interest: Petroleum Engineering

Re: Line spading controls

Post by ww2i »

Once identified during the spading list review that there are some spades still in place, that should have triggered any system to take care of any risk of taking the system in operation.
That could have been an MOC process but practically this is not possible to assess the risk in detail during a PSSR or may be within PSSR, some member must have asked for change management to follow.