Inspection PM Plan - Primary Reformer Furnace

Materials Science, Metallurgy, Welding, NDTs, Reliability Assessment, Failure Analysis, etc.
Post Reply
qaisarabbas
Core Member
Posts: 134
Joined: 23 Mar 2010, 15:21
Area of interest: Metallurgy Engineering

Inspection PM Plan - Primary Reformer Furnace

Post by qaisarabbas »

Dear members,

I am attaching a checklist for PM plans of all the components related to Reformer Furnace (in our case, its Foster Wheeler, Terrace Type Design). Please comment or suggest if I am missing any inspection check on any of the component. Request to share the similar checklist if someone has a more comprehensive. Thank you all.
Primary Reformer Furnace - PM Plan Checklist.jpg
You do not have the required permissions to view the files attached to this post.
Q. Abbas
sakib321
Posts: 64
Joined: 02 Aug 2010, 04:06
Area of interest: Metallurgy Engineering

Re: Inspection PM Plan - Primary Reformer Furnace

Post by sakib321 »

Check the hangers expansion and contraction in hot(just after shut down) and cold condition
Sakib Jalal
ben
Posts: 165
Joined: 24 Aug 2010, 03:11
Area of interest: Mechanical Engineering

Re: Inspection PM Plan - Primary Reformer Furnace

Post by ben »

It looks fine to me.
Do introduce certain other advanced inspection techniques for catalyst tubes.
arcpro
Posts: 299
Joined: 16 Apr 2010, 18:46
Area of interest: Manufacturing Engineering

Re: Inspection PM Plan - Primary Reformer Furnace

Post by arcpro »

A comprehensive plan.
Thanks for sharing.
inconel
Posts: 21
Joined: 08 Jun 2010, 13:17
Area of interest: Metallurgy Engineering

Re: Inspection PM Plan - Primary Reformer Furnace

Post by inconel »

Thanks for sharing
Regards,

Inconel
Nabeel Ahmed Qureshi
Core Member
Posts: 87
Joined: 04 Apr 2010, 09:38
Area of interest: Mechanical Engineering

Re: Inspection PM Plan - Primary Reformer Furnace

Post by Nabeel Ahmed Qureshi »

Thanx for sharing.
NAQ
aterao
Posts: 3
Joined: 12 Nov 2010, 16:12
Area of interest: Mechanical Engineering

Re: Inspection PM Plan - Primary Reformer Furnace

Post by aterao »

The inspection plan well covered all aspects. However, it doesn't contain your acceptance criteria. Do include OD measurement of catalyst tubes at outlet tube sections. Think of renewal as the strain goes above 3%.

Ultrasonic attenuation test looks well engineered & robust, because we pay handsome sum to these guys... But do ask them to provide you with the recorded data of the attenuation test for each individual tube instead of manipulated grading of tubes...
arcpro
Posts: 299
Joined: 16 Apr 2010, 18:46
Area of interest: Manufacturing Engineering

Re: Inspection PM Plan - Primary Reformer Furnace

Post by arcpro »

Aterao,
You made a valid point regarding OD measurement. That was missing.